The top-down method of estimating project time and costs that is useful for projects requiring the same task, group of tasks, or product repeated several times, especially if it is labor intensive, is the ______________.
a) function point
b) ratio
c) apportion
d) consensus
e) learning curves

Respuesta :

parisannthornton parisannthornton
  • 04-08-2021
The answer is e) learning curves
Answer Link

Otras preguntas

what factor is not a part of the highway traffic system
which function for prokaryotes is described by binary fission
The correct form for writing binomial nomenclature is _____. Genus species Genus species genus Species genus Species
What is proximate cause?
NiCl3 is a strong electrolyte. Determine the concentration of each of the individual ions in a 0.400 M NiCl3 solution.
Identify one latitude line that runs through the united states of America as well as china
Enter the solution to the inequality in the box. −6x−4≥−2(x−4)
what is the molar mass of feso4 • 7h2o
A compound verb consists of a plural verb associated with two different subjects True or False?
T What's the circumference of a circle with a diameter of 45 centimeters? A. 141.4 centimeters B. 6,361.7 centimeters C. 282.7 centimeters D. 70.7 centim