15men can complete a piece of work in25days. how many men should be added to complete the same work in15days.​

Respuesta :

mhanifa
mhanifa mhanifa
  • 04-08-2021

Answer:

  • 10 men

Step-by-step explanation:

Amount of work done by 15 men is:

  • 15 men *25 day = 15*25 man*days

Same work can be done by 25 men, in 15 days, so 10 more men should be added.

Answer Link
abovejosh
abovejosh abovejosh
  • 04-08-2021
Answer: 10 men explanation: guy above me
Answer Link

Otras preguntas

Which is the minimum quantity of fruits that should be eaten daily
Writers who turned away from the harsh realities of industrial life were part of which cultural movement? Realism Romanticism Impressionism photography
How many times was the world supposed to end 2010-2017?
Which lists the main components of Darwin’s theory of evolution
What effect does distance have on the speed of a moving object
10 POINTS BIG BRAINLESS FOR WHO EVER ANSWER WRITE Which is the best thesis for a research report? 1. Marie Curie was a brilliant scientist characterized by i
Jeremiah is factoring 0.64t^24 - 9 by using the rule, a^2 - b^2 = (a+B)(a-b). What will he use for the value of a? A.0.08t^12 B. 0.8t^12 C. 0.64 D. 0.8 I think
the quotient of a number and three is equal to negative eight
What is from this number 1 3 5 7 9 1 13 15 get to 30 only with 5 number?
2-3 main human factors that have impacted the environment of central and South America. write a 5 sentence paragraph explaining these factors.