If 24 electricians can wire some new houses in 15 days, how many electricians would be required to do the job in 12 days?.

Respuesta :

shishirshrestha989
shishirshrestha989 shishirshrestha989
  • 04-01-2022

Answer:

here,

electrician/days

24 - 15

x(let). -12

direct proportion,

then,

exchange X up 24 down

or,24*15=12*X

or,24*15divided by 12=X

X=30

hence,30 electrician required to do complete in 12 days

Answer Link

Otras preguntas

FACTORIZE. 9x2y-24xy2-16y3 solve it
The Radius of a sphere is 5 feet. find the area of the great circle of this sphere
What is the approximate circumference if the circle that has a center at (2,1) ans passes through the point (2,5). 1. 8 units 2. 13 units 3. 25 units 4. 50 unit
what time is 9 hours and 30 minutes before. 4:25
The number of waves that pass a particular point in a unit of time is called the __________ of the waves. (a) rarefaction (b) compression (c) amplitude (d) freq
The diameter of your bicycle wheel is 25 inches. How far will you move in one turn of your wheel?
What is the coefficient of y in the expression 12+3y-2x?
What is the coefficient of y in the expression 12+3y-2x?
you have a full cylindrical glass of water that stands 8 inches tall and has a radius of 1.5 inches .if you pour the water into a larger cylindrical glass that
A history quiz consists of five true-false questions. If you guess on each question, then the probability of answering all five questions correctly is approxima